378.3MW Egbema Power Plant: FG Pledge to expedite completion
434MW Geregu II Power Station (NIPP), Kogi State

378.3MW Egbema Power Plant: FG Pledge to expedite completion

The Federal Government has vowed to accelerate the completion of the 378.3 megawatts Egbema Power Plant in Imo State, saying it is currently 70 per cent completed.
The Nigeria Minister of Power, Adebayo Adelabu, made this known during the weekend at an inspection visit to the power plant, commending the Governor of Imo, Hope Uzodinma, for his dedication to collaborating with the Niger Delta Power Holding Company to complete the power projects in the state.
Adelabu who was accompanied by the Managing Director of the NDPHC, Mr Chiedu Ugbo, the minister praised President Bola Tinubu for signing the 2023 Electricity Act, which allows states to participate in the electricity sector.
He said the completion of the Egbema power plant and associated transmission projects will improve the electricity supply in Imo State and beyond.
While giving his speech, Uzodinma pledged to collaborate with the NDPHC to ensure the completion of the plant to improve the electricity supply in the State.
He said the collaboration would ensure the completion of the 378.3MW Egbema Power Plant, along with the 330/33KV switchyard, the Omoku-Egbema-Owerri-Alaoji 330KV DC transmission lines projects, and the Owerri transmission substation expansion project.
“The projects are at various stages with the power plant at 70 per cent completion stage. The collaboration between the Imo State Government and NDPHC aims to enhance electricity supply and energise homes and businesses in Imo State through the completion of the Egbema Power Plant and associated transmission infrastructure,” a statement by Adelabu’s spokesperson, Bolaji Tunji, said on Sunday.